Press Information

MHPS Receives Order for 2 Steam Turbine and Generator Sets for Coal-fired Ultra-supercritical-pressure Thermal Power Plant in Morocco from Daewoo Engineering & Construction of Korea

Print

Yokohama, October 2, 2014 - Mitsubishi Hitachi Power Systems, Ltd. (MHPS) has received an order for two sets of a 693 megawatt (MW) class steam turbine and generator (STG) for a project to construct a coal-fired ultra-supercritical-pressure(Note) thermal power generation plant in Safi, Morocco. The two STG sets, for Units No.1 and No.2 at the plant, will be delivered through Daewoo Engineering & Construction Co., Ltd., a major construction company in Korea that is undertaking engineering, construction and procurement (EPC) on the project. The two thermal units are slated to commence operation in 2018.